Production Operations Schedule
Operations Schedule Production
0..n

Operations Type attribute

Operations Request Production
0..n

(Production order)

Segment Requirement (Unit Procedure) Production
0..n 0..n

Equipment Specification Personnel Specification Contributing Contributing Segment Requirement (Operation) Production Segment Requirement (Phase) Production
0..n 0..n 0..n 0..n

Resource Use attribute

Material Specification Being Consumed

Material Specification Being Produced

5_11_ISA8895_Interoperability_B2O_Example-

2

Quality Operations Schedule (for Material)
Operations Schedule Quality
0..n

Operations Request Quality
0..n

(QA Test Operation) (Inspection)

Segment Req Quality Segment Req Quality
0..n 0..n

(Sampling)

Segment Req Quality

(Testing)

0..n 0..n

0..n

0..n

Equipment Spec Contributing Analyzer

Personnel Spec Contributing Laboratorian

Material Spec Being Consumed Reagents

Material Spec Being Tested Sample Material Property Tested characteristic

0..n

5_11_ISA8895_Interoperability_B2O_Example-

3

Example of mapping SAP Inspection Lot (Physical Sample)
Inspection Lot Operation Material Number Work Center
1..m

Operation Request Segment (Operation) Equipment Spec Segment (Sampling) Material Spec
1 1..m

Physical Sampling 1

1..n

Segment (Testing) Material Spec
1 1

1..n

Characteristic
1

Method

Material Property

ERP

ISA-95 4

5_11_ISA8895_Interoperability_B2O_Example-

Quality Operations Schedule (for Equipment)
Operations Schedule Quality
0..n

Operations Request Quality
0..n

(Equipment Test program) (Inspection)

Segment Req Quality
0..n

Segment Req Quality

(Testing)

0..n 0..n

0..n

Equipment Spec Contributing Testing device

Personnel Spec Contributing Inspector

Equipment Spec Being Tested Machine under testing Equipment Property Tested characteristic

0..n

5_11_ISA8895_Interoperability_B2O_Example-

5

Quality Operations Schedule (for Personnel)
Operations Schedule Quality
0..n

Operations Request Quality
0..n

(Examination) (Test)

Segment Req Quality

0..n

Personnel Spec Contributing Examinator

Personnel Spec Being Tested Examinee Personnel Property Tested skills

0..n

5_11_ISA8895_Interoperability_B2O_Example-

6

Maintenance Operations Schedule
Operations Schedule Maintenance
0..n

Operations Request Maintenance
0..n

(Maintenance Request)

Segment Req Maintenance
0..n

(Maintenance Request Subject)

Segment Req Maintenance

(Maintenance Order)

Equipment Spec Being Repaired Machine to be repaired

0..n

0..n

0..n

0..n

Equipment Spec Contributing Tools

Personnel Spec Contributing Repairmen

Material Spec Contributing Lubricant, cleanser

Physical Asset Spec Being Repaired Machine under maintenance

0..n

5_11_ISA8895_Interoperability_B2O_Example-

7

Inventory Operations Schedule
Operations Schedule Inventory
0..n

Operations Request Inventory
0..n

(Transfer order)

Segment Requirement (Transfer Operation) Inventory

0..n

0..n

0..n

Equipment Specification Personnel Specification Material Specification Contributing Contributing Being Moved From

Material Specification Being Moved To

0..n

5_11_ISA8895_Interoperability_B2O_Example-

8

Mixed Operations Schedule
Operations Schedule

0..n

Operations Request mixed
0..n

Operations Request Production

Operations Request Maintenance

Operations Request Quality

Operations Request Inventory

Segment Requirement Mixed

Segment Requirement Segment Requirement Segment Requirement Segment Requirement Production Maintenance Quality Inventory

0..n

0..n

0..n

0..n

0..n

0..n

Material Spec Being Moved From

Material Spec Being Moved To

Equipment Spec Contributing Machine allocated To production

Material Spec Being Consumed Material incorporated

Material Spec Being Produced Material created

Material Spec Being Tested Sample and QA results

Raw Material dispensing From Warehouse to production area

Inventory Operations

Production Operations

Quality Operations

5_11_ISA8895_Interoperability_B2O_Example-

9


Johann Sebastian Bach. the music closest to silence, closest, in spite of its being so highly organized, to pure, one-hundred-degree proof Spirit" (Aldous Huxley, Island)